Data processing: measuring – calibrating – or testing – Measurement system – Performance or efficiency evaluation
Reexamination Certificate
2007-04-10
2007-04-10
Barlow, John (Department: 2863)
Data processing: measuring, calibrating, or testing
Measurement system
Performance or efficiency evaluation
Reexamination Certificate
active
10744743
ABSTRACT:
A systematic approach is presented for the development and implementation of cost-effective transmission asset maintenance strategies. The overall concept and methodology are based on transmission reliability and risk management and address the value of preventive maintenance activities. This may help electric network utilities conduct maintenance policy assessment, region-wide criticality analysis, and optimal maintenance resource allocation and task scheduling.
REFERENCES:
patent: 5107497 (1992-04-01), Lirov et al.
patent: 5331579 (1994-07-01), Maguire et al.
patent: 5699403 (1997-12-01), Ronnen
patent: 5798939 (1998-08-01), Ochoa et al.
patent: 6041287 (2000-03-01), Dister et al.
patent: 6167352 (2000-12-01), Kanevsky et al.
patent: 6321187 (2001-11-01), Squier et al.
patent: 6330935 (2001-12-01), Systermans
patent: 6671634 (2003-12-01), Koutlev et al.
Kuntz, P.A., “Optimal reliability centered vegetation maintenance scheduling in electric power distribution system”,Ph.D. Thesis of UOW,1999.
Radmer, D.T., “Predicting Vegetation-Related Failure Rates in Electric Power Distribution System”,Master Thesis of UOW,1999, 1-51.
Chow, M. et al., “Analysis and Prevention of Animal-Caused Faults in Power Distribution System”,IEEE Transactions On Power Delivery,1995, 10(2), 995-1001.
Frazier, S.D., “Suggested Practices for Reducing Animal-Caused Outages”,IEEE Industry Application Magazine,Jul./Aug. 1996, 25-31.
IEEE Guide for Improving the Lightning Performance of Electric Power Overhead Distribution Lines,1410-1997, Approved Jun. 26, 1997, 1-39.
Tolbert, L.M., et al., “Reliability of Lightning Resistant Overhead Distribution Lines”,IEEE I&CPS,May 1999, 147-152.
Short, T.A., “Lightning Protection of Overhead Distribution Lines”, http://www.pti-us.com/pti/consult/lightning protection of overhead.htm, Sep. 14, 2001, 9 page.
Short, T.A., “Monitoring Results of the Effectiveness of Surge Arrester Spacings on Distribution Line Protection”, http://www.pti-us.com/pti/consult/lico.htm, Sep. 14, 2001, 12 pages.
“Electric Power Industry Applications of Lightning Data”,Global Atmospherics Lightning Detection,http://www.glatmos.com/industries/article1.html, Sep. 17, 2001, 7 pages.
McDermott, T.E. et al., “Lightning Protection of Distribution Lines”,IEEE Transactions on Power Delivery,Jan. 1994, 9(1), 138-152.
“Working Group Report: Calculating the Lightning Performance of Distribution Lines”,IEEE Transactions on Power Delivery,1990, 5(3), 1408-1417.
IEEE Recommended Practice for the Design of Reliable Industrial and Commercial Power Systems(Gold Book), IEEE Std 493-1997, Approved Dec. 16, 1997, 1-492.
Horton, W.F., et al., “The failure rates of overhead distribution system components”,IEEE,1991, 713-717.
Horton, W.F., et al., “Determination of Failure Rates of Underground Distribution System Components from Historical Data”,IEEE,1991, 718-723.
Stember, L.H., et al., “Analysis of Field Failure Data on HMWPE and XLPE Insulated High-Voltage Distribution Cable”,IEEE Trans on Power Apparatus,1985, vol. PAS-104(8), 1979-1985.
Cizelj, R.J., et al., “Components Reliability Assessment Using Quantitative and Qualitative Data”,Relaibility Engineering and System Safety,2001, 71, 81-95.
Gupta, S., et al., “Predicting the Failure Rates of Overhead Distribution Lines Using an Adaptive-Fuzzy Technique”, 2001, 1-5.
“IEEE Guide for Failure Investigation, Documentation and Analysis for Power Transformers and Shunt Reactors”,IEEE Standards Board,1992, C57, 125-1991.
Frimpong, G.K., “Facilities Assessment Management Engineering(An Overview)”,ABB Internal Report,Jun. 9, 2000, 19 pages.
Canadian Electricity Association 2000 Annual Service Continuity Report on Distribution System Performance in Electrical Utilities, May 2001, 1-78.
Canadian Electricity Association, Forced Outage Performance of Transmission Equipment- for the period Jan. 1, 1994 to Dec. 31, 1998, Feb. 2000, 1-142.
Wang, Z., “Artificial Intelligence Applications in the Diagnosis of Power Transformer Incipient Faults”,Virginia Tech, Ph.D., dissertation,Aug. 2000, 1-105.
Densley, J., “Ageing Mechanisms and Diagnostics for Power Cables- An Overview”,IEEE Electrical Insulation Magazine,Jan./Feb. 2001, 17(1), 14-22.
Marsden, H. et al., “Cable Diagnostics Business Technology Evaluation”,ABB ETI Technical Report,#BDC-R-01002,Jan. 2001, 1-66.
Morrison, W.G., “Using New Technology to Improve Reliability of an Industrial Cable Distribution System”,IEEE Trans. On Industry Applications,Mar./Apr. 1992, 28(2), 275-281.
Pultrum, E. et al., “Dutch Distribution Cable Performance”,IEEE Colloquium on “MV Paper Cables: Asset or Liability”?Capenhurst, Apr. 21, 1998, 3/1 thru 3/6.
Brown, R.E., “Probabilistic Reliability and Risk Assessment of Electric Power Distribution Systems”,DistribuTECH Conference, San Diego, Ca,Feb. 2001.
Brown, R.E., “Modeling the Impact of Substations on Distribution Reliability”,IEEE Transactions on Power Systems,Feb. 1999, 14(1), 349-354.
Carvalho, A. et al., “Functional Specification as Driver for Technical/Economical Optimisation of Substation”,Presentation at CIGRE Session, Paris, France,2000, 1-10.
Beshir, M.J. et al., “Comparison of Monte Carlo Simulation and State Enumeration Based Adequacy Assessment Programs: CREAM and COMREL”,IEEE,1996, 438-444.
Van Casteren, J.F.L. et al., “Reliability Assessment in Electrical Power Systems: The Weibull-Markov Stochastic Model”,IEEE Transactions on Industry Applications,May/Jun. 2000, 36(3), 911-915.
Lang, B.P. et al., “Power Distribution System Reliability Planning Using a Fuzzy Knowledge-Based Approach”,IEEE Transactions on Power Delivery,Jan. 2000, 279-284.
Volkmann, C.A. et al., “A Probabilistic Approach to Distribution System Reliability Assessment”,Third International Conference on Probabilistic Methods Applied to Electric Power Systems,Jul. 3-5, 1991, 169-173.
Nuqui Reynaldo
Pan Jiuping
Tang Le
ABB Research Ltd.
Pretlow Demetrius
LandOfFree
Value-based transmission asset maintenance management of... does not yet have a rating. At this time, there are no reviews or comments for this patent.
If you have personal experience with Value-based transmission asset maintenance management of..., we encourage you to share that experience with our LandOfFree.com community. Your opinion is very important and Value-based transmission asset maintenance management of... will most certainly appreciate the feedback.
Profile ID: LFUS-PAI-O-3767894