Data processing: financial – business practice – management – or co – Automated electrical financial or business practice or... – Health care management
Reexamination Certificate
2006-09-26
2006-09-26
Diaz, Susanna M. (Department: 3623)
Data processing: financial, business practice, management, or co
Automated electrical financial or business practice or...
Health care management
Reexamination Certificate
active
07113915
ABSTRACT:
A system for managing a project being a plurality of jobs including construction jobs wherein some of the jobs don't require completion of other jobs and remaining jobs require completion of at least one of the independent jobs and/or completion of other jobs in the plurality of jobs. The system separates jobs into lists according to their dependency on other jobs and assigns manpower according to expense, expressed as man days, for completing the job withoin a list period. The system is preferably implemented in conjunction with a panoramic camera and computer. One section of the computer screen displays a 360° field of view of the project. Another section displays a table showing the interrelationship of the jobs. Alpha-numeric indicia, entered by a mouse/keyboard at job locations on the image section of the screen are indexed to jobs scheduled in the table which is entered in the text section of the screen.
REFERENCES:
patent: 5918219 (1999-06-01), Isherwood
patent: 2002/0082883 (2002-06-01), Hankinson
patent: 2002/0087381 (2002-07-01), Freeman et al.
patent: 2003/0069716 (2003-04-01), Martinez
patent: 2004/0030992 (2004-02-01), Moisa et al.
patent: 07-049910 (1995-02-01), None
patent: 09-261619 (1997-10-01), None
Shih et al. “A Preliminary Application of Panoramic Supervision System in Construction Site.” Information Visualization, 2001. Proceedings. Fifth International Conference on Jul. 25-27, 2001, pp. 103-108.
Jennings, K. Denise. “Webcams for Contractors.” Construction Executive, pp. 32-34, Jun. 2003.
Retik et al. “Mobile Hybrid Virtual Reality and Telepresence for Planning and Monitoring of Engineering Projects.” Department of Civil Engineering. University of Strathclyde, Glasgow, retr.from [URL: http://www.ee.surrey.ac.uk/Personal/R.Bowden..] Oct. 28, 2005.
“Competitive Advantage: Project 98.” Businessworld, Jan. 27, 1998.
“Gantt chart—a searchCIO definition” web site [URL:http://web.archive.org/web/20030713134550/http://searchcio.techtarget.com/sDefinition/0,,sid19—gci33139...], last updated on Apr. 30, 2003.
Montemayor Susanne
Smith Robert Samuel
Diaz Susanna M.
Smith Robert Samuel
LandOfFree
System for scheduling and monitoring a project does not yet have a rating. At this time, there are no reviews or comments for this patent.
If you have personal experience with System for scheduling and monitoring a project, we encourage you to share that experience with our LandOfFree.com community. Your opinion is very important and System for scheduling and monitoring a project will most certainly appreciate the feedback.
Profile ID: LFUS-PAI-O-3590730