Sardine-bone construction method for large-section tunnel

Hydraulic and earth engineering – Underground passageway – e.g. – tunnel – Boring

Reexamination Certificate

Rate now

  [ 0.00 ] – not rated yet Voters 0   Comments 0

Details

C405S266000, C405S287100, C299S011000

Reexamination Certificate

active

06520718

ABSTRACT:

TECHNICAL FIELD
The present invention relates to a construction method for boring a large-section tunnel safely and quickly by reinforcing and improving the ground surrounding the tunnel to develop artificial ground arches.
BACKGROUND ART
A construction method for boring a tunnel through weak ground by reinforcing the ground to increase its capability of self-support and prevent the tunnel from collapsing is shown in publication of patent application JP-1989-137094.
In this prior art, injection holes are drilled from the face of the tunnel into the ground surrounding the tunnel toward the tunneling direction. Then injection pipes are inserted into the drilled holes to inject grout into the injection holes for reinforcing the ground surrounding the tunnel. After the ground is reinforced, the reinforced part of the ground is excavated, and timbered and/or lined. The steps stated above are repeated to bore the tunnel.
DISCLOSURE OF THE INVENTION
In this prior construction method, however, drilling and injecting steps for reinforcing the ground, and excavating and lining steps for tunnel boring have to be repeated one after another at the face, so that the construction works are complicated and inefficient which result in a longer construction period.
An object of the present invention is to provide a construction method for boring a large-section tunnel safely and quickly by reinforcing and improving in advance the ground over the full length of the tunnel section.
In the sardine-bone construction method for large-section tunnel (SBR Construction Method) of the present invention, for solving the problem stated above, drifts are bored through the full length of the tunnel section, then curved holes inclined in forward or backward directions at an angle of about 45 degrees are drilled at preset intervals from the drifts along the peripheral edges of the sections of the tunnel by using ordinary small bore rock drills and curved steel pipes, the steel pipes are pulled off after injection pipes are inserted into the drilled holes, grout is injected into the ground surrounding the tunnel through the injection pipes to develop artificial ground arches, then the tunnel is excavated, suspension forms are advanced and concrete is placed for secondary lining, whereby the tunnel is bored.
In the construction method, at first, drifts are quickly bored through the full length of the tunnel section. Then curved holes are drilled by using rock drills and curved steel pipes, the steel pipes are pulled off after injection pipes are inserted into the drilled holes, grout is injected into the ground surrounding the tunnel through the injection pipes. Because these steps are executed from the drifts, the works are efficiently completed. It is different from doing the works at the face at intervals of excavating.
In addition, drilling curved holes and injecting grout can be simultaneously executed at more than one places so that the artificial ground arches are quickly developed, since the steps of reinforcing and improving ground are executed after the drift is bored through the full length of the tunnel.
At the face, only excavating and lining steps are continuously executed, so that the boring works are uncomplicated and efficient.
A top drift is suitable for developing artificial ground arches when the tunnel is bore d by adopting an upper half section advancing excavation method.
If drifts are placed in the middle of the side-walls of the tunnel, curved holes are drilled upward along the peripheral edges of the section of the tunnel from the drifts to the top of the tunnel. This is suitably used for excavating upper half unit of the tunnel through weak ground.


REFERENCES:
patent: 528367 (1894-10-01), Harris
patent: 721830 (1903-03-01), Perin
patent: 3631680 (1972-01-01), Thomson
patent: 3916630 (1975-11-01), Arsuaga
patent: 3968655 (1976-07-01), McGlothlin
patent: 4365913 (1982-12-01), Bonvoisin
patent: 5118220 (1992-06-01), Furumi et al.
patent: 5678957 (1997-10-01), Lipsker
patent: 01137094 (1989-05-01), None
patent: 05018194 (1993-01-01), None
patent: 06017590 (1994-01-01), None
patent: 06074715 (1994-09-01), None
patent: 06264698 (1994-09-01), None
patent: 06096844 (1994-11-01), None
patent: 07076988 (1995-03-01), None
patent: 10046978 (1998-02-01), None
patent: 11159275 (1999-06-01), None
patent: 11-200762 (1999-07-01), None
patent: WO99/28595 (1998-03-01), None

LandOfFree

Say what you really think

Search LandOfFree.com for the USA inventors and patents. Rate them and share your experience with other people.

Rating

Sardine-bone construction method for large-section tunnel does not yet have a rating. At this time, there are no reviews or comments for this patent.

If you have personal experience with Sardine-bone construction method for large-section tunnel, we encourage you to share that experience with our LandOfFree.com community. Your opinion is very important and Sardine-bone construction method for large-section tunnel will most certainly appreciate the feedback.

Rate now

     

Profile ID: LFUS-PAI-O-3181070

  Search
All data on this website is collected from public sources. Our data reflects the most accurate information available at the time of publication.