ABSTRACT:
When the process plan made for execution is corrected based on the process correction condition, the variation amount in each of processes based on the process correction condition is calculated as the probability distribution using the probability distribution data generated by obtaining the probability distribution from the variation-amount prediction value of each of the processes. Thereby, the influence degree on other processes when the process is corrected can be estimated not simply as the propagation of the variation fixed value but so as to be more suited to the actual circumstances in accordance with the attribute information and the past variation patterns of the process.
REFERENCES:
patent: 5623404 (1997-04-01), Collins et al.
patent: 5918219 (1999-06-01), Isherwood
patent: 6237915 (2001-05-01), Ledet et al.
patent: 6397202 (2002-05-01), Higgins et al.
patent: 6591232 (2003-07-01), Kassapoglou
patent: 6675127 (2004-01-01), LaBlanc et al.
patent: 6889196 (2005-05-01), Clark
patent: 6895383 (2005-05-01), Heinrich
patent: 7113914 (2006-09-01), Spielmann et al.
patent: 2002/0138318 (2002-09-01), Ellis et al.
patent: 2002/0194040 (2002-12-01), Kornfein et al.
patent: 2002/0198750 (2002-12-01), Innes et al.
patent: 2003/0023470 (2003-01-01), Labbi
patent: 2003/0187766 (2003-10-01), Akashi
patent: 2004/0073505 (2004-04-01), Wright
patent: A-10-240804 (1998-09-01), None
patent: 2000200303 (2000-07-01), None
Ranasinghe, Malik, Quantification and management of uncertainty in activity duration networks Construction Management and Economics, vol. 12, No. 1, Jan. 1994, Abstract.
Finley, Eric D. et al., Project Scheduling Risk Assessment Using Monte Carlo Methods Cost Engineering, vol. 36, No. 10, 1994, pp. 24-28.
Ock, Jong H., Activity duration quantification under uncertainty: Fuzzy set theory application Cost Engineering, vol. 38, No. 1, Jan. 1996.
Yang, Kum-Khiong, Effects of erroneous estimation of activity durations scheduleing and dispatching a single project Decision Sciences, vol. 27, No. 2, Spring 1996, pp. 255-290.
Hernandex, Toms, Software Solutions Building Design & Construction, vol. 40, No. 11, Nov. 1999, pp. 38-40.
Royer, Paul, Risk management: The undiscovered dimension of project management Project Management Journal, vol. 31, No. 1, Mar. 2000.
Mills, Anthony, A systematic approach to risk management for construction Structural Survey, vol. 19, No. 5, 2001, pp. 245-252.
Prasanta, K. Dey et al., Project Time Risk Analysis Through Simulation Cost Engineering, vol. 43, No. 7, Jul. 2001, pp. 24-32.
Isidore, Leroy J. et al., Integrated probabalistic schedules and estimates from project simulated data Construction Management and Economics, vol. 19, 2001, pp. 417-426.
Palisade.com Web Pages Palisade Inc, 2000, Retreived from Archive.org Sep. 23, 2005.
Scramsoftware.com Web Pages SCRAM Software, Apr. 2000, Retrieved from Archive.org Apr. 5, 2006.
Pyron, Tim, Team Yourself Microsoft Project 98 in 24 Hours Sames Publishing, May 7, 1998, ISBN: 0-672-31258-1.
Marchman, David A., Construction Scheduling with Primavera Project Planner Delmar Publishers, Aug. 14, 1997, ISBN: 0827370865.
Rose, Aaron, The Role of Probablility in Scheduling Transactions of the American Association of Cost Engineers, 1981, Abstract.
Dawood, Nashwan, Estimating project and activity duration: a risk management approach using network analysis Construction Management and Economics, vol. 16, 1998, pp. 41-48.
Basu, Abhi, Practical Risk Analysis in Scheduling AACE International Transactions, 1998.
Dawson, R.J. et al., Practical Proposals for Managing Uncertainty and Risk in Project Planning International Journal of Project Management, vol. 16, No. 5, Oct. 1998, Abstract.
Hammond, Chris, @Risk arms Excel with Risk Analysis InfoWorld, vol. 22, No. 12, Mar. 20, 2000.
Isidore, Leroy et al., Integrated Range Estimating an Stochastic Scheduling Cost Engineering, vol. 43, No. 2, Feb. 2001.
Araki Kenji
Kudoh Makoto
Nishikawa Youichi
Nonaka Hisanori
Yokota Takeshi
Hafiz Tariq R.
Hitachi Plant Technologies, Ltd.
Jarrett Scott L.
Mattingly ,Stanger ,Malur & Brundidge, P.C.
LandOfFree
Project risk management system utilizing probability... does not yet have a rating. At this time, there are no reviews or comments for this patent.
If you have personal experience with Project risk management system utilizing probability..., we encourage you to share that experience with our LandOfFree.com community. Your opinion is very important and Project risk management system utilizing probability... will most certainly appreciate the feedback.
Profile ID: LFUS-PAI-O-2749541