ABSTRACT:

The present invention relates to gassed bulk slurry explosives in general, and gassed bulk explosives of the emulsion slurry type in particular,
More specifically the invention relates to a method for loading and sensitising a slurry explosive in a borehole or filling and sensitising a slurry explosive in shells and cartridges
Bulk slurry explosives are generally loaded from socalled SMS (Site Mixed Slurry)loading trucks or from a socalled SSE (Site Sensitised Emulsion)-loading truck directly into the customers borehole. In the cartridging of gassed slurry explosives the equipment used is in principle similar to that which is used for SMS loading, with exception that in general water lubrication is not used since this will reduce the quality of the slurry product due to reduction of the energy and detonation properties of the explosive.
The principle for a bulk-SMS-loading truck which supplies a so-called micro balloon sensitised emulsion slurry, has been described in U.S. Pat. No. 5,526,633.
It is usually desirable that slurry explosives have a high viscosity so that the slurry does not flow out in joints and fissures in a rock, during or after loading, or so that the slurry does not flow out of boreholes which are drilled and charged upwards. In order to pump such highly viscous slurry explosives from a loading truck to a borehole it is often necessary to lubricate the loading pipe on the inside with a thin water film which reduces the pump pressure. It is known from U.S. Pat. No. 4,273,147 that by using a water film or water to which ammonium nitrate has been added, which lubricates the loading pipe, it is possible to pump the slurry through long and thin loading pipes without having a dangerously high pumping pressure.
Before U.S. Pat. No. 4,273,147 was generally known, all loading of bulk slurry explosives took place without the use of “lubricating water”, but also today such loading may occur when low viscosity slurries are used which are only pumped over relatively short distances, or in the cartridging of slurry explosives.
In U.S. Pat. No. 4,615,752 it shown how one may pump a low viscosity emulsion with water lubrication and then at the end of the pipe thicken (i.e. increase the viscosity of) the emulsion. In order to obtain sufficient lubrication the water film must have a given thickness which is normally attained by adding water in the form of a cylindrical ring in an amount of 2-5% of the total slurry weight. Sometimes water in amounts of above 5% by weight may be necessary.
More and more explosive producers have gradually realised the advantages in using a so called gassed slurry instead of a slurry which has been sensitised with micro balloons or other porous solid additives.
When a slurry is to be gassed chemically, this may either be done by adding the gassing agent to a slurry matrix (i.e. unsensitised slurry explosive) Inside a mixing chamber, usually Immediately before the slurry enters the slurry pump to be pumped down into the borehole or in a cartridge, or the gassing agent may be added to the slurry at the end of the loading pipe immediately before a static mixing means.
The gassing agent may either be transported to the nozzle of the pipe in a separate pipe, or the gassing agent may be added to the lubricating water as described in GB 2 204 343 A.
However, commercially such a pipe end mixing is practised only to a very limited extent due to several practical difficulties connected therewith. Finding suitable equipment which fits into a pipe end and which has a sufficient mixing effect is difficult, but also bringing the gassing agent to the end of the pipe in a reproducable and practical manner represents a problem.
In spite of said difficulties with gassing at the end of a loading pipe it also offers many advantages that a slurry may be gassed at the end of the loading pipe both in a SMS- and a SSE-system,
In this manner increased security is attained in view of the fact that all production of the explosive takes place in the borehole or at a safe distance from the production equipment. The loading pipe will only contain small amounts of explosive even if there should be a stop in the loading procedure for unexpected reasons. (Today a SMS loading pipe may contain up to 50 kg of explosive), There is no pumping or, mechanical working of the final explosive. If ignition means should detonate during the introduction of a loading pipe or during the pumping of a slurry, the detonation cannot propagate into the loading pipe back to the loading truck.
As mentioned above, GB 2 204 343 A describes a method in which the gassing agent is conveyed to the end of the pipe by being added to the aqueous lubrication film. However, this involved certain problems.
Firstly, by means of the technique described in GB 2 204 343 A it is not possible to gas emulsions emusified with nitrite as described in Norwegian Patent No. 155 691. Thus, one can not obtain a safe and reproducable gassing if the mixing of gassing agent and emulsion takes place with low intensity, which often occurs with a limited static mixing of gassing agent at the end of the pipe.
Further, it is not possible to add ammonium nitrate (AN) to the lubricating water, as described in U.S. Pat. No. 4,273,147, since AN will react with nitrite, and gassing will then occur during the preparation of the lubricant/gassing agent is mixture.
When a loading pipe is left standing with slurry for a certain period. the water film will gradually be absorbed by the slurry, and in the start-up it may be necessary with a large amount of water film to avoid a loading stop. With the state of art this will result in varying slurry density and an undesired quality of the product.
In order to reduce the density of the slurry to a given level it is necessary to add a certain amount of gassing agent with a given concentration. As mentioned above, the water film will represent 2-5% by weight of the total amount of slurry, and if the water film shall serve as both water film and gassing agent, the concentration of gassing agent must be reduced drastically in comparison with that which is normally used. This means that at the end of the pipe it is necessary to add a larger amount of gassing agent than usual, but also a gassing agent which is highly diluted in comparison with that which is normally used. It has been found to be more difficult as well as less efficient to carry of the mixing with a greater amount of a gassing agent which in addition is diluted.
Further, one looses the possibility of being able to vary the density in one and the same borehole by adding little or much gassing agent, because this will have an effect on the water lubrication, and problems with the water lubrication will result in a clogging of the loading pipe and production stop.
According to the invention there is provided a method of loading and sensitising a slurry explosive in a borehole or filling and sensitising a slurry explosive in shells and cartridges. The method is characterised in that to the unsensitised slurry explosive, after it has been pumped with a slurry pump into a loading pipe, there is added a gassing agent as a thin string centrally in the loading pipe, and unsensitised slurry explosive and the gassing agent are mixed at the nozzle of the loading pipe, so that the unsensitised slurry explosive is not sensitised to the final slurry explosive until it has been loaded into boreholes or filled in shells/cartridges.
In the loading of boreholes lubricating water is suitably injected along the wall of the loading pipe.
Addition of the gassing agent may take place after the slurry pump, but preferably before a possible water lubrication. In principle the gassing agent may be added anywhere in the loading pipe, after the slurry pump, and independently of whether or not “lubricating water” is used.
“The string” of gassing agent follows the slurry flow without being mixed therewith, through the loading pipe, which may be as much as 100 meters long, and will finally, at the end of the loading pipe, become intimately mixed with the slurry so that

LandOfFree

Say what you really think

Search LandOfFree.com for the USA inventors and patents. Rate them and share your experience with other people.

Rating

Method for loading slurry explosives in blast holes or... does not yet have a rating. At this time, there are no reviews or comments for this patent.

If you have personal experience with Method for loading slurry explosives in blast holes or..., we encourage you to share that experience with our LandOfFree.com community. Your opinion is very important and Method for loading slurry explosives in blast holes or... will most certainly appreciate the feedback.

Rate now

     

Profile ID: LFUS-PAI-O-2970280

  Search
All data on this website is collected from public sources. Our data reflects the most accurate information available at the time of publication.