ABSTRACT:
The present invention relates to designating that durations of specific tasks are estimated or tentative. The user can indicate estimated durations by the sheet mode or the dialog mode. Estimated duration characters are symbols of uncertainty, such as “?”, that indicate that the duration entries are not fixed and final, but may need to be adjusted in the future. The user can select an option to not display the estimated duration character even though the estimated field for the task is set. The user can also select an option to have new tasks that are created have estimated duration characters until the user chooses to enter a duration value. The program can also filter the task list to display only tasks that have estimated duration characters.
REFERENCES:
patent: 4813010 (1989-03-01), Okamoto et al.
patent: 5249240 (1993-09-01), Nakayama
patent: 5291397 (1994-03-01), Powell
patent: 5303170 (1994-04-01), Valko
patent: 5524201 (1996-06-01), Shwarts et al.
patent: 5548506 (1996-08-01), Srinivasan
patent: 5798950 (1998-08-01), Fitzgerald
patent: 5918219 (1999-06-01), Isherwood
patent: 6108673 (2000-08-01), Brandt et al.
patent: 6317700 (2001-11-01), Bagne
patent: 6322366 (2001-11-01), Bergan et al.
patent: 6571285 (2003-05-01), Groath et al.
patent: 6681211 (2004-01-01), Gatto
patent: 6687902 (2004-02-01), Curtis et al.
patent: 6889196 (2005-05-01), Clark
patent: 04223851 (1992-08-01), None
patent: WO 01/80124 (2001-10-01), None
Using Microsoft Project 4 for Windows, by Tim Pyron et al., Apr. 20, 1994, pp. 1-2, 5, 35, 38, 55, 57, 61-62, 118, 181, 214, 325, 341, 448-449, 454-455, 548, 469, 478-479, 516, 554, 618-619, 632, 668 and 675.
Using Microsoft Project 4 for Windows, by Tim Pyron et al, Que Corp, 1994, pp. i-II, 2, 5, 35, 38, 55, 57, 61-62, 99, 18, 136, 150, 181, 214, 325, 341, 374, 448-449, 454-455, 469, 473-474, 478-479, 516, 548, 554, 586, 617, 618, 619, 623, 626, 632, 668 and 675.
The Artificial Intelligence Dictionary. pp. i-ii and 240. Ellen Thro, 1991, Microtrend Books, Slawson Communications, San Marcos, CA 92069-1436.
Microsoft Project 2000 Product Enhancements Guide Microsoft, Oct. 1999.
Tim Pyron, Sams Teach Yourself Microsoft Project 98 in 24 Hours Sams, May 7, 1998, ISBN: 0672312581.
Pyron et al., Using Microsoft Project 2000 Special Edition, Que; Sep. 21, 2000, ISBN: 0789722534.
Carl S. Chatfield et al., Microsoft Project 2000 Step by Step Microsoft Press, Jun. 3, 2000, ISBN: 0735609209.
Ron Black, Complete Idiot's Guide to Project Management with Microsoft Project 2000 Alpha, Apr. 5, 2000, ISBN: 0789722712.
Primavera Project Planner—Planning and Control Guide Version 3.0 Primavea Systems, Inc., 1999.
A Guide to the Project Management Body of Knowledge Project Management Institute, 1996, ISBN: 1-8880410-13-3.
Cummings, Nigel, @Risk for Project Delivers Richer Picture Feb. 1999, OR Newsletter.
Palisade.com—Web Pages Mar./Jun. 2000, Retrieved from Archive.org Sep. 23, 2005.
Finley, Eric et al., Project Scehduling Risk Assessment Using Monte Carlo Methods Cost Engineering, Oct. 1994, vol. 36, No. 10, pp. 24-28.
Ranasinghe, Malik, Quantification and management of uncertainty in activity duration networks Construction Management and Economics, Jan. 1994, vol. 12, No. 1, Abstract.
Yahng, Kum-Khiong, Effects for Erroneous Estimation of Activity Duration on Scheduling and Dispatching a Single Project Decision Sciences, Sprin 1996, vol. 27, No. 2, pp. 255-290.
Ock, Jong H., Activity duration quantification under uncertainty, Fuzzy set theory application Cost Engineering, Jan. 1996, Vo 38, No. 1.
Dawood, Nashwan, Estimating project and activity duration: A risk management approach using network analysis Construction Management and Economics, Jan. 1998, vol. 16, No. 1, Abstract.
Marsh, Thomas, Palisade upgrades @Risk software Corporate Finance, Sep. 1998, No. 166.
Cummings, Nigel, @Risk delivers richer picture Operational Research Society—OR Newsletter, Feb. 1999.
ScramSoftware.com Web Pages Apr. 2000, Retrieved from Archive.org Apr. 5, 2006.
Palisade.com Web Pages May-Jun. 2000, Retrieved from Archive.org Apr. 7, 2006.
Pyron, Tim, Teach Yourself Microsoft Project 98 in 24 hours Sams Publishing, May 1998, ISBN: 0-672-31258-1.
Essentials of expressing measurement uncertainty The NIST reference on Constants, Units and Uncertainty, Retrieved from Physics.nist.gov, Apr. 7, 2005.
Bentsen Brett A.
Doerr Eric W.
Zhang Qin
Hafiz Tariq R.
Jarrett Scott L.
Microsoft Corporation
Perkins Coie LLP
LandOfFree
Method and system for visually indicating project task... does not yet have a rating. At this time, there are no reviews or comments for this patent.
If you have personal experience with Method and system for visually indicating project task..., we encourage you to share that experience with our LandOfFree.com community. Your opinion is very important and Method and system for visually indicating project task... will most certainly appreciate the feedback.
Profile ID: LFUS-PAI-O-3818041