Metal curb installation system and method

Road structure – process – or apparatus – Traffic steering device or barrier – Curb

Reexamination Certificate

Rate now

  [ 0.00 ] – not rated yet Voters 0   Comments 0

Details

Reexamination Certificate

active

06695525

ABSTRACT:

FIELD OF THE INVENTION
The present invention relates to sidewalk and road construction and more particularly to systems and methods for installing concrete curb, straight and curved, faced with steel to protect the concrete from damage due to cars, trucks and snow plows.
BACKGROUND OF THE INVENTION
At the present time, in cities and in metropolitan areas, a sidewalk is located at a side of a road, e.g., street or roadway. The sidewalk is elevated typically 7″ above the road (the reveal), and a curb is used to separate the road from the sidewalk. The curb has a nearly vertical face which ranges from 18′ to 27″ depending on the thickness of the road and the reveal of the curb. The bottom of the curb is buried 11″ to 20″ below the road, and has a nearly horizontal portion which lines up with the sidewalk. There is a ½″×6½″×18-27″ premolded bituminous expansion joint filler (EJF) between curb sections and a ¼″ expansion joint between the curb and sidewalk for expansion and contraction. When the curb and sidewalk are poured simultaneously, a ½″ thick expansion joint (EJF)is generally used between the curb and sidewalk.
Plain concrete is most often used for such curbs. In high traffic areas, such as busy city streets, the concrete is rapidly chipped, cracked and broken, so a hard stone, such as granite, is often used. However, the costs of cutting, transporting and installing elongated granite curb members is high and may be prohibitive.
Steel has been used for many years to face concrete curb since it is strong and can resist damage caused by the impact of the truck wheels and snow plows when installed along streets having heavy vehicle traffic. Steel faced concrete curb is less costly than granite but as good as, or superior, in resisting damage. However, steel curb-facing (steel curb) is heavy and, because it is heavy and clumsy to handle, it is costly to install. A typical steel curb is 20 feet long, asymmetrical, and weighs about 340 pounds. It usually requires a four-man crew to lift and install a steel curb or two men with a lifting machine. The curb, during its installation, must be exactly aligned with a string guidance line. The surfaces of adjacent steel curbs must align smoothly where they join each other. If one steel curb extends beyond or above the next, it will present a sharp edge which can cut vehicle tires and present a tripping hazard to pedestrians.
To rebuild an existing road, generally the curb to be replaced is removed. A trench, 11 to 18 inches deep and 18 to 24 inches wide, is then dug. Using surveyor instruments, including a surveyor's level, a continuous guidance string is strung as a guide for the curbs. The string is supported by long steel (primary) stakes, for example, ¾-inch diameter and 36-inch long. The primary stakes are about 50 feet apart and driven into the earth at the bottom of the trench, generally along the back of the future curb. The string is the guide for the line (sidewise location) and grade (elevation) of the new curb. The curb may be straight and may be curved.
The next steps in the conventional method is to drive other stakes 1½″ behind the string line, about 5 feet apart, into the earth at the bottom of the trench. These stakes hold a back (wood) form in its vertical position such that the face of the wood is on the line of the guidance string. The wood form is usually made, for example, from 2×8 (inch) and 2×12 (inch) lumber held together to form a nominal 2″×20″(actually 1½″×19″). The forms (front and back) are the mold for containing the concrete slurry which is later poured into the form. The steel curb is placed in the space between the form, against the front form.
The steel curb has a nearly vertical face, which may be about 11″. Two stacks of bricks are formed, spaced, for example 19 feet apart, on the bottom of the trench. The stacks of brick range in height, typically, from 10″ high for an 18″ deep curb to 19″-27″ for other curbs. The steel curb is lifted into the trench and set on the stacks of bricks. The curb has a series of protruding steel studs for anchoring the steel curb to the concrete curb. The stacks of brick are shifted so they are directly under the end studs (typically 3″ up and 9″ from each end) so they are in the position to support the curb. The stacks are inherently unstable and often topple when the curb is placed upon them. But, even if they were stable, because of the high center of gravity and a asymmetrical shape of the steel curb, the curb will not stand by itself on a stack of brick. To compensate for this when the steel curb is correctly positioned relative to the string, and while two men balance the curb, the wooden forms are placed behind and in front of the steel curb and clamped.
Each steel curb must be lifted, positioned and adjusted so that it is at the correct height relative to the guidance string. Usually wooden shims are placed on top of the stacks of bricks and beneath the steel stud for a finer adjustment. However, the conventional method described for the placement and adjustment of the steel curbs is slow, inexact and labor-intensive. The steel curb must be steadied by two men, one at each end, while 2 or 3 other men place the front and back forms and clamp them together. Wood spacers, 36″ apart, are positioned between the steel curbs and wood forms to keep the steel curb and wood forms from collapsing inwardly. This conventional method is expensive because of the time required, the number of men in the crew, their skill and their relatively high wages and fringe benefits.
SUMMARY OF THE INVENTION
In accordance with the present invention, to lay a line of straight steel curbs, a trench is dug and a guidance string line is positioned in the trench.
In the primary method, in accordance with the present invention, a series of sheet metal or plastic benches, one for each piece (section) of steel curb, is provided to hold and position the straight steel curb. The benches are aligned relative to the string line. The benches are raised, or lowered, by placing or removing dirt beneath their bottom plates, until the benches are at the correct elevation. Each bench has two front plates at ⅜″ apart, for expansion, each bracket having a support shelf to position and support the bottom edge of the steel curb. The benches are formed of sheet metal or plastic and are left in the trench after the concrete slurry has been poured. One bench supports the leading end of the previous steel curb and the trailing end of the next steel curb which is to be set. At that time, or after a series of straight curbs are positioned in the trench, wooden forms are removably placed on the benches. A wood form is positioned at the front (the side toward the road) against the lower 2-3″ of the face of the curb. A wood form is positioned at the back, with the form extending to the height of the top lip portion (curve-dover portion) of the curb. The concrete slurry is then poured between the form and allowed to harden. The wood forms are then removed, the trench partially filled with compacted earth and crushed stone, and the road and sidewalk are laid down.
In an alternative method, especially useful for setting curved curbs, two benches are tied to the curb, one at the leading end and one at the center. The bench and curb are then lifted by the work crew and placed in the trench in the curb's line and grade. The trailing end of the curb is placed in the bracket of a previously positioned bench.
A corner steel curb, used at street corners and generally 85° to 95°, is positioned in a different way. In the first step, the corner curb is lowered by the work crew into the trench and positioned on wooden blocks which lay on the floor of the trench. In the second step the tangents of the corner steel curb are aligned with intersecting streets. In the third step, metal stakes

LandOfFree

Say what you really think

Search LandOfFree.com for the USA inventors and patents. Rate them and share your experience with other people.

Rating

Metal curb installation system and method does not yet have a rating. At this time, there are no reviews or comments for this patent.

If you have personal experience with Metal curb installation system and method, we encourage you to share that experience with our LandOfFree.com community. Your opinion is very important and Metal curb installation system and method will most certainly appreciate the feedback.

Rate now

     

Profile ID: LFUS-PAI-O-3286579

  Search
All data on this website is collected from public sources. Our data reflects the most accurate information available at the time of publication.