ABSTRACT:

BACKGROUND OF THE INVENTION
This invention relates to an operations, maintenance, and administration part for an information network system that adopts a common channel signaling system, such as a signaling system No. 7.
To maintain an information network system which adopts a common channel signaling system and includes a plurality of exchanges (e.g. electronic switching systems) connected to one another, it is necessary to execute an OMAP test such as an MRVT (MTP (Message Transfer Part) Routing Verification Test) or an SRVT (SCCP (Signaling Connection Control Part) Routing Verification Test). The OMAP test is carried out according to an operation, maintenance, and administration protocol (OMAP) defined as Q.753 and Q.754 recommendations by ITU-T (International Telecommunication Union—Telecommunication Standardization Sector).
A conventional operations, maintenance, and administration part (hereinafter referred to simply as a maintenance part) is incorporated in each of the exchanges to execute the OMAP test. The maintenance part includes an input/output interface, a test starting and managing section, and a test message processing section.
The input/output interface is connected to an external maintenance terminal such as a workstation. The external maintenance terminal supplies the maintenance part with a command set representative of test information to make the maintenance part execute the OMAP test.
When the maintenance part receives the command set, the starting and managing section decides whether a starting data managing resource (i.e. a memory area) registering the same test information is already secured in a first register (or memory) or not. If the starting data managing resource is already secured in the first register, the starting and managing section informs the external maintenance terminal of an error through the input/output interface. On the other hand, if the starting data managing resource is not secured in the first register yet, the starting and managing section secures a new starting data managing resource in the first register and registers the test information in it. Then, the starting and managing section requests the test message processing section to transmit a test message.
When the test message processing section receives the request from the starting and managing section, it secures a test information managing resource (a memory area) in a second register and registers the test information read out from the new starting data managing resource. Then, the test message processing section establishes a connection with a destination exchange specified by the test information and transmits the test message to the destination exchange. In this time, the test message processing section starts up a timer for deciding a maximum waiting time. The exchange, which transmits the test message, is called a source exchange to distinguish from the destination exchange.
When the destination exchange receives the test message, it secures a test information managing resource and registers test information included in the test message therein. Then the destination exchange produces a response message on the basis of the test information registered in the test information resource and transmits the response message to the source exchange. Next, the destination exchange releases the test message processing resource thereof.
When the test message processing section of the source exchange receives the response message, it gives a notice of a result of the OMAP test to the test starting and managing section in response to the response message. Next, the test message processing section releases the test information managing resource thereof (or deletes the test information from the second register).
When the starting and managing section receives the notice of the result of the OMAP test, it transfers the notice to the external maintenance terminal through the input/output interface. Furthermore, the starting and managing section releases the staring data managing resource in this time. In other words, the starting and managing section deletes the test information from the first register.
The external maintenance terminal analyzes the notice of the result of the OMAP test and maintains the information network system on the basis of the analysis result.
If the test message processing section of the source exchange does not receive the response message before the timer clocks the maximum waiting time, it begins an audit trial.
If the external maintenance terminal supplies a plurality of command sets to the maintenance part, the maintenance part secures a plurality of starting data managing resources in the first register and a plurality of test information managing resources in the second register individually corresponding to the command information sets. The maintenance part also secures other test information managing resources in the second register when it receives test messages from the other exchanges.
In the following, consideration will be made about restart of the exchange.
The restart can be classified into two levels. One is a relievable level and the other is an unrelievable level. The restart of the unrelievable level means complete initialization and reactivation. The unrelievable level restart is carried out after a system down. On the other hand, the restart of the relievable level means initialization with keeping internal state of memories. The relievable level restart is carried out after temporary malfunction such as lack of memory areas. Hereinafter, the term of “restart” signifies the relievable level restart.
Now, it is assumed that the starting data managing resource is secured in the starting and managing section. In addition, it is assumed that the test information managing resource is secured in the test message processing section.
In this state, if the restart is made in the exchange, the test starting and managing section keeps the starting data managing resource and the test message processing section keeps the test information managing resource.
BY the way, there is a case where the OMAP test comes to an abnormal end when the restart is made in the middle of execution of the OMAP test. Accordingly, it is desired that the OMAP test is executed again when the restart is made in the exchange. However, the conventional maintenance part can not receive the same command set that represents the test information registered in the starting data managing resource.
If the OMAP test based on the test information registered in the starting data managing resource comes to a normal end, the starting data managing resource is released. It takes several seconds to execute the OMAP test. Accordingly, the command set which is not received by the conventional maintenance part immediately after the restart will be received in several seconds.
On the other hand, the conventional maintenance part executes an audit trial when the OMAP test comes to an abnormal end. It takes several hours to execute the audit trial. The starting data managing resource relating to the OMAP test is not released until the audit trial is finished. Thus the OMAP test can not be executed again for several hours in this case. This is a problem in the conventional maintenance part.
The conventional maintenance part further has another problem as follows.
There is a case that the test message processing section is in waiting state for receiving the response message after the restart even though it does not transmit the test message. In this case, the test message processing section never receives the response message. Moreover, the test message processing section never carries out a time out transaction because the timer is not started. Therefore, the OMAP test comes to the abnormal end. As mentioned above, the conventional maintenance part executes an audit trial when the OMAP test comes to the abnormal end. During the audit trial, the test information managing resource and the starting data managing resource are not released.
SUMMARY OF THE INVENTION
It is therefore an object of this inv

LandOfFree

Say what you really think

Search LandOfFree.com for the USA inventors and patents. Rate them and share your experience with other people.

Rating

Operations, maintenance, and administration part capable of... does not yet have a rating. At this time, there are no reviews or comments for this patent.

If you have personal experience with Operations, maintenance, and administration part capable of..., we encourage you to share that experience with our LandOfFree.com community. Your opinion is very important and Operations, maintenance, and administration part capable of... will most certainly appreciate the feedback.

Rate now

     

Profile ID: LFUS-PAI-O-3141105

  Search
All data on this website is collected from public sources. Our data reflects the most accurate information available at the time of publication.